New Railroad Bridge

River road closed for new bridge. After announcing a limited number of days of daytime shutdowns for the road east of Plattsmouth along the Missouri River over the next month or so the company constructing the new railroad bridge has now informed county officials it will be a complete shutdown (24/7, 7 days a week) during that time.

“Due to the existing electrical line issue and additional exposure to local traffic, …we will need to change our daytime shutdown to full shutdown mode,” said Larry Dean Folkner of Ames Construction. That now means River Road will be closed from Wednesday (3/7) through Friday (5/4).

Another full shutdown remains on the schedule for November 5th, 2012 through February 28th, 2013.