State roads One and Five Year Program schedules. The Nebraska Department of Roads` 2013 program runs from July 1, 2012, to June 30, 2013. The Five Year Program is for 2014 through 2018.
The Cassgram reprots Projects in Cass County on the One Year Program:
-Joint sealing on 16.5 miles of Interstate 80 from Mahoney State Park to Millard / $1.98 million (estimated cost)
-Culvert placement south of Mahoney State Park / $230,000
-Resurfacing 6.1 miles of Highway 66, South Bend east and west / $758,000
-I-80 Platte River Bridge shore stabilization / $112,000
---Projects on the Five Year Program in Cass County:
-Milling, resurfacing, and bridge repair on 13.9 miles from Nebraska Highway 50 to Highway 34 / $5.25 million
-Murray viaduct repair on Highway 1 / $3.2 million
-Resurfacing 9.4 miles of Highway 34/75 from Union to Plattsmouth / $5 million
-Resurfacing 4.3 miles of Highway 34 from Highway 1 to Plattsmouth / $3.18 million
-Resurfacing 1.4 miles of Highway 34 in Plattsmouth / $1.05 million
-Resurfacing 1.9 miles and bridge work on the 13k Spur at Weeping Water / $3.03 million
-Milling and resurfacing on 10.8 miles of Highway 34 from Highway 63 to Nebraska Highway 50 / $6.72 million
-Milling and resurfacing 5 miles of Highway 34 west of Union / $2.74 million
-Resurfacing 4 miles of Highway 63 from Highway 34 to Alvo / $1.57 million
-Grading, culvert and surfacing on 6.1 miles of Highway 63 north of Alvo / $10 million
-Milling and resurfacing 3.7 miles of Highway 66 from I-80 to South Bend / $1.46 million
-Interchange and bridge repair on Highway 66 at the Mahoney Road intersection / $2.79 million
-Resurfacing 4.8 miles of Highway 66 from South Bend to Highway 50 / $3.24 million